Tiger Den curved LED storefront replacement at Changi Airport Terminal 4, Singapore
Flexible & Curved

Tiger Den Changi Airport T4 – Curved LED Display Replacement

A staged curved LED replacement coordinated around airport access, protected finishes and controlled handback.

Changi Airport T4, Singapore

Curved LED storefront replacement planned for controlled night work at Changi Airport T4.

Solution
Flexible & Curved
Location
Changi Airport T4, Singapore
Scope
Curved LED replacement, configuration & commissioning

Project Planning Considerations

Planning Considerations

  • Assess the existing control environment, display geometry, pixel-pitch relationship and power/network infrastructure before deciding how closely a replacement should follow the original installation.
  • For airport retail work, plan the actual permitted access window, equipment method, floor protection, work sequence and clean handback before entering the site.
  • Use a controlled staged method for removal, power/control/cabling, replacement modules and final configuration so restricted night work remains organised and accountable.
Explore Hospitality & Public-Space LED Solutions

Project Overview

Tiger Den is a bar outlet at Changi Airport Terminal 4 whose storefront already incorporated a curved LED display above the entrance. After many years of operation, the original display had deteriorated and the client engaged ETA Visual to remove the existing system and replace it with a new curved LED display. The work required more than changing panels: the replacement had to respect the existing installation environment, fit within controlled airport access windows and protect the completed retail interior throughout the process.

Keeping the Replacement Compatible with the Existing System

During the site survey, ETA Visual identified that the existing display used a NovaStar control environment. Because the operating team was already familiar with that environment, the replacement was designed around a familiar system where practical.

The new display was also planned to closely match the original screen's physical dimensions and pixel pitch. This helped minimise modification work and avoided unnecessary changes to the existing power and network infrastructure.

Planning Work Around Airport Access and Finished Interiors

Large installation activities involving tall ladders or lifting equipment had to be scheduled within permitted late-night access windows, when passenger traffic was lower. The work method therefore had to be developed around the available airport access rather than a conventional daytime installation programme.

The existing carpet was protected with timber boards before installation activity began. This created a working surface for equipment and construction activity while protecting the finished airport retail interior.

Project at a Glance

VenueTiger Den, Changi Airport Terminal 4
Project typeExisting curved LED display replacement
Existing control environmentNovaStar
Working periodLate-night installation window
Installation sequenceFour-night phased replacement
Site protectionTimber boards over existing carpet
Tool controlPre-approved and inventoried tools

Engineering Challenges & Solutions

Challenge 1

Replacing an Ageing Curved Display in a Live Airport Retail Environment

The Challenge

The existing curved LED system had to be removed and replaced without treating the location like an empty construction site. The project had to retain a controlled approach to the existing infrastructure, finished interior and airport operating environment.

ETA Visual's Solution

ETA Visual planned the replacement in defined stages, matched the new display closely to the existing installation where practical and coordinated the work method around controlled site access and completed finishes.

Challenge 2

Working Within Restricted Night Access

The Challenge

Daytime passenger traffic and restrictions on larger installation activities meant that conventional daytime work was not suitable for the replacement.

ETA Visual's Solution

The installation was arranged as a phased four-night sequence so removal, power and control work, new modules, and final alignment and commissioning could be completed in an organised order.

Four-Night Installation Sequence

The first night covered removal of the existing LED modules, power cables, receiving cards and related components. The second night introduced the new power system, receiving cards and cabling, followed by new LED modules on the third night.

The final night focused on module flatness, a new control-program configuration and commissioning. The old display program could not simply be reused, so the replacement system was configured and verified on site after physical alignment was complete.

Tool Control and Airport Handback

Tools brought into the controlled airport environment were submitted for approval in advance and identified as required. The equipment list was checked before entry and reconciled against the approved inventory when leaving the site.

This disciplined process, together with carpet protection and defined night stages, helped keep the replacement work organised within the airport environment.

Key Lessons From the Project

Airport LED replacement work benefits from designing the new system around compatible interfaces where practical, confirming permitted working windows early and treating protection, tool control and site handback as core delivery requirements.

Why This Project Was Successful

1

Existing-system awareness

The replacement considered the familiar NovaStar control environment and existing site interfaces where practical.

2

Night-work sequencing

Removal, cabling, module installation and commissioning were separated into clear night stages.

3

Finished-interior protection

Timber boards protected the completed carpet before equipment and installation activity began.

4

Controlled-site discipline

Pre-approved, inventoried tools supported accountable entry and exit from the airport environment.

The Final Result

  • The ageing curved LED display was replaced through a staged four-night work sequence.
  • The replacement retained a familiar control environment where practical and reduced unnecessary changes to existing infrastructure.
  • The completed airport retail interior was protected during installation through planned floor protection and controlled site procedures.

Frequently Asked Questions

ETA Visual LED display and AV system project backdrop
Let's Talk

Ready to light up
your space?

Tell us about your space and we'll get back with a free, no-obligation site survey and recommendation.

WhatsApp
+65 8038 9034
Email
perry.peng@etavisual.com
Office
12 New Industrial Road, #02-02C, Morningstar Centre, Singapore 536202

Click to upload or drag & drop

Up to 5 files · 8MB each · PDF, images, docs

We use your details and any files to reply to this enquiry and arrange the requested work. Please do not upload passwords or unrelated sensitive data. Privacy Notice

More Flexible & Curved projects