Ant Group Expo Booth — Flexible & Curved installation by ETA Visual at Singapore Expo
Flexible & Curved

Ant Group Singapore Exhibition – Large Curved LED Display Installation

Two P2.5 curved exhibition displays delivered through pre-assembly, parallel installation and event-ready control.

Singapore Expo

Two P2.5 curved LED displays coordinated for a Singapore exhibition booth with a three-day build-up window.

Solution
Flexible & Curved
Pixel pitch
P2.5
Location
Singapore Expo
Scope
Supply, installation & commissioning

More angles

Ant Group Expo Booth — view 2 — Flexible & Curved installation by ETA Visual

Project Planning Considerations

Planning Considerations

  • Prepare and test cables, receiving cards and control components before arrival so restricted venue time can focus on physical installation and commissioning.
  • For suspended booth displays, confirm overhead steelwork, lifting-hoist readiness, other-contractor work zones and access sequence before the LED installation begins.
  • Plan control-hardware location, content-upload workflow and dismantling manpower alongside the display build rather than as separate end-of-event tasks.
Explore Event LED Display Solutions

Project Overview

Ant Group required two large curved LED displays for its Singapore exhibition booth, with only a three-day build-up period before the event. ETA Visual prepared key components before delivery and increased manpower so both screen work fronts could progress at the same time. The delivery also depended on coordination with the suspended overhead structure, other booth contractors and the practical requirement to operate and clear the exhibit within the event schedule.

The Three-Day Installation Challenge

The project involved two large curved displays and a short exhibition build-up period. ETA Visual increased manpower and installed the two screens simultaneously so both work fronts could progress together instead of waiting on one another.

This parallel approach was paired with pre-delivery preparation, allowing the team to focus on installation and commissioning once the display work could begin on site.

Preparation Before Site Installation

Cables, receiving cards and control components were prepared and tested at ETA Visual's premises before delivery. This reduced individual connection work at the exhibition venue and made better use of the restricted build-up time.

The two P2.5 displays used 320 × 160 mm soft LED modules, which can be assembled into different inner-curve and outer-curve configurations to suit exhibition-booth geometry.

Coordination With the Suspended Booth Structure

The displays were suspended from overhead steel beams, so installation could begin only after the overhead structure and lifting hoists were complete. This created a dependency on other contractors that had to be accommodated in the site schedule.

Other teams were also installing tables, cabinets and advertising graphics around the booth. Work areas and timing were coordinated before construction, while unexpected changes were addressed through flexible on-site coordination.

Project at a Glance

ClientAnt Group
ApplicationSingapore exhibition booth LED display
DisplaysTwo large curved LED displays
Pixel pitchP2.5
LED module320 × 160 mm soft LED module
Installation deadlineThree days
Control systemProcessors and media players integrated inside the displays
Content updateWireless upload by mobile or computer application
Dismantling windowApproximately four hours

Engineering Challenges & Solutions

Challenge 1

Quality Control Under a Tight Schedule

The Challenge

Speed was required, but the two suspended curved displays still had to be installed and configured as a reliable event system during a compressed build-up period.

ETA Visual's Solution

ETA Visual followed its standard delivery and inspection process, controlled module-to-module installation tolerance to approximately 0.5 mm in line with the project standard and configured the control system around the client's event use.

Challenge 2

Keeping Control Hardware Out of the Booth Sightline

The Challenge

Placing video processors and media players on the floor would have introduced visible network cables running up to the suspended displays and reduced the visual cleanliness of the booth.

ETA Visual's Solution

ETA Visual integrated the video processors and media players inside the suspended LED displays, reducing exposed cabling and keeping the control system close to the screen system.

Wireless Content Upload

With the media player installed inside an elevated display, using a USB drive or external HDMI cable would have been inconvenient. Operators could instead upload videos from the ground using a mobile application or computer application.

Reliable Exhibition Operation and Rapid Dismantling

Both displays operated normally throughout the three-day exhibition without reported problems. After the event, the team had approximately four hours to dismantle the screens and clear the site, so removal sequencing and manpower were planned as part of the original delivery method.

Key Lessons From the Project

Pre-assembly, parallel installation, concealed control hardware and an agreed dismantling sequence can help make a short exhibition build-up more manageable while retaining an organised quality-control process.

Why This Project Was Successful

1

Detailed Pre-Planning

Cables, receiving cards and control components were prepared and tested before delivery to reduce connection work at the venue.

2

Parallel Installation

Additional manpower allowed the two display work fronts to progress simultaneously during the three-day build-up.

3

Integrated Control Hardware

Processors and media players were installed inside the suspended displays to reduce visible cabling.

4

Event-Ready Delivery

Installation tolerance, control setup, wireless content workflow and post-event removal were considered as one exhibition delivery process.

The Final Result

  • Two P2.5 curved LED displays installed within the documented three-day exhibition build-up.
  • Control processors and media players integrated inside the suspended displays for a cleaner booth appearance.
  • Wireless content upload enabled from ground level through a mobile or computer application.
  • Dismantling and site clearance were planned within an approximately four-hour post-event window.

Frequently Asked Questions

ETA Visual LED display and AV system project backdrop
Let's Talk

Ready to light up
your space?

Tell us about your space and we'll get back with a free, no-obligation site survey and recommendation.

WhatsApp
+65 8038 9034
Email
perry.peng@etavisual.com
Office
12 New Industrial Road, #02-02C, Morningstar Centre, Singapore 536202

Click to upload or drag & drop

Up to 5 files · 8MB each · PDF, images, docs

We use your details and any files to reply to this enquiry and arrange the requested work. Please do not upload passwords or unrelated sensitive data. Privacy Notice

More Flexible & Curved projects